Install Day 5

Continued tweaking Lotem and 43wide.

Thursday, March 6, 2008

Install Day 3 and 4

Connect Lotem, 43wide, and Epson.

Difficulties: add renderstation on domain, but log in as local admin, adjustments on 43wide, PDF to Epson.

Tuesday, March 4, 2008

Install Day2

Added Domains.
Created Doman user... Prinergy.User.
Set up users.
Installed first client.

To do: output plate with ellipse dot.
clean up harmony curves.

Tomorrow: Lotem, proofers.

Monday, March 3, 2008

Install Day 1

Day 1 is installing the hardware.
The Servers did not come pre-installed with the Server names as requested, so Prinergy had to be re-installed... twice.
We also had to run a (network) line... this took some time.

Tomorrow's plan is to get it on the domain, RSS setup, 'transfer' all curves, connect all printers, and Lotem